Yesterday on site we leveled the floor with cement, to prepare for tiling next week.
Due to the minimal time we have for construction, it was very important to plan everything out as much as possible To not waste anytime on site, leveling should be done on Saturday to allow adequate drying over Sunday; to lay concrete for leveling means all plumbing rough-in underfloor need to do done by Friday afternoon; to enable underfloor plumbing, floor finish removal should take priority in demolition and finish by mid morning... Etc etc... Pretty much setting a goal (project completion) and working backwards.
So far everything has been progressing smoothly, and everyone on site and neighbors seem to be excited about the future transformation... I can't wait.
1 July 2012
From the ground up