Majority of the fitout was flatpacked and assembled off-site, to work in parallel with the site work in order to reduce amount of time required.
The entire off-site process has taken almost as long as the site work to date, which means, without off-site construction planned into the design, the construction time could have been doubled.
Snap shots at the off-site "assembly line" over the past weeks...
arrived all flatpacked...these are only half of the components. |
painting of the components before assemblage |
...drying... |
one of the first few units assembled |
colour matching with the sample (the little piece of plywood) - this is a pretty good match. We did have some difficulty with application method, but we ended up with a good result |
full-on!! there are a few types of boxes, some are better painted after assemblage, some are better painted prior |
call in the helpers! the system was designed to minimise skilled labour requirement, so when necessary we can get more people to help |
neatly packed! there are still more to go, but probably 90% done! |