Flatpacking Wu-Gu

One very large aspect of this project is the extensive use of off-site assembly.

Majority of the fitout was flatpacked and assembled off-site, to work in parallel with the site work in order to reduce amount of time required.

The entire off-site process has taken almost as long as the site work to date, which means, without off-site construction planned into the design, the construction time could have been doubled.

Snap shots at the off-site "assembly line" over the past weeks...

arrived all flatpacked...these are only half of the components.

painting of the components before assemblage

...drying...

one of the first few units assembled

colour matching with the sample (the little piece of plywood) - this is a pretty good match. We did have some difficulty with application method, but we ended up with a good result

full-on!!
there are a few types of boxes, some are better painted after assemblage, some are better painted prior

call in the helpers!
the system was designed to minimise skilled labour requirement, so when necessary we can get more people to help

neatly packed!
there are still more to go, but probably 90% done!