I meant to say: a quick update on a quick-moving project....

Here are the quick lines from site before weekend:
Student lounge side:
They are working on form work of roof structure over student lounge
Chapel side:
They are almost finished working on steel reinforcing bars for 2nd floor over wc, storage, entrance lobby and 2nd floor of chapel. 
They are pouring concrete on to chapel building up to 2nd floor level on Saturday.

 

 

 

 

 

 

 