Due to poor weather condition, there is delay in construction progress but the construction team is still pushing for the in-situ concrete base and walls completion before end of 2010. The timber beams are being manufactured offsite in the factory during the cold season.
![]()  | 
| on site the formwork is ready to wall height, and building base is already poured; to the right of building is the entry to garage | 
![]()  | 
| from the inside; looking very crowded with the scaffolding... | 
![]()  | 
| offsite in factory. this is the beam on top of the concrete walls, where the roof rafters will come down to interlock with | 
![]()  | 
| the roof rafters being carefully shaped and trimmed one by one in the factory | 